I had to re-rig the big tarp that was blown down a couple weeks earlier. It was a hot-sunny weekend so we really needed the shade. The tarp took most of the day Saturday leaving just enough time to finish off the headers. We used more scrap lumber to bring them out flush with the outside of the framing so we would have something to nail the sheathing to above window and door openings.
We developed a pretty good system where Carolyn is the cutter and I am the nailer. Once we have have a good piece, Carolyn can use it to mark the next and so on. This way, she is usually ahead of me.
By mid-afternoon, we had gotten about a third of the sheathing on the front wall.