Working on a big canvas: 40 acres on Lookout Mountain, Alabama.


Purchase and Location

I bought this property in 2005 and named it Richmond Woods for my father who taught me about nature and respect for the wild. It's located in Alabama near the Alabama/Georgia state line. The small nearby village of Mentone, AL has been a mountain retreat for 150 years for people escaping the summer heat of Birmingham and Atlanta. My companion, Carolyn, has helped me every step of the way.

A Cottage in the Woods
When you were little, did someone read fairy tales to you? Invariably, there was mention of a cottage in the woods. Our plan is to build such a place: handmade, no architect plans, buying local materials or using salvaged materials. The purpose of this blog is to document our progress.

Saturday, August 21, 2010

Floor Finishing

This is how I planned to sand the floor. A 4" wide belt sander. Big mistake. Jas'n tried to tell me. After hours and hours of coarse sanding we had only about 30% of the floor done and we still had two more grits to go.



Jas'n's new boss loaned him a real floor sander and I rented a floor edger. We headed up Thursday evening to get an early start Friday morning. By the time we broke for lunch (about 5 hours after starting) we had finished the coarse sanding with 36 grit.



After lunch we followed up with 80 grit and finished out with 100. Then I quickly mixed up my mother's secret furniture finish solution (50/50 boiled linseed oil and turpentine) adding a touch of Minwax for color.



Another hour on my hands and knees with a rag and the first coat was done - and so were we. Another two coats followed up with some paste wax and a buffer and you will see the most beautiful fine-furniture-like wood floor ever!

Saturday, July 31, 2010

Hot Hot Hot

This has been the hottest July in a long time. Here's what we've managed to get done...

Built & installed a crawl-space door.



Added hot and cold waterlines for kitchen sink. Before you go gettin' all excited, there is still NO running water. This is just thinking ahead. Initially, I will install a small reservoir in the attic for a gravity feed to the sink. No 'hot and cold' but rather 'attic temperature'.

Added electrical outlet for stove. Same as above. No electricity yet, just thinking about the future.

Finished hanging drywall - mudded, sanded, and primed. Waiting for that globe-trotting Carolyn to get back to the good ole USA and do some serious painting.




Laid hardwood floor. This is 5-inch red oak toung-and-groove 3/4 inch thick kiln-dried plank flooring. I chose #3 grade for its character and for its price. But because this stuff is hard as iron, I'm going to pay the price when it comes time to sand it. :(





Cut and framed porch attic access opening. There is not a lot of head room above the porch but a good bit of storage space for items seldom accessed.

Wired, insulated, and paneled screen porch walls and ceiling. Only two outlets one on each long wall and a single overhead for a fan/light combo. We insulated because we will eventually use this space in the winter by inserting panels into the screen openings. When not needed (9 months of the year) the panels will live in the porch attic out of the way. We used the same bead-board plywood for the ceiling as in the main cabin just for continuity (and also so there would be no overhead sanding). The walls are paneled with 5/8 T-111 plywood stained with the same sealer as the exterior of the cabin. This provides good strength in sparsely-studded walls.





Next up are:
1) sanding and finishing the oak floor
2) painting the interior walls
3) interior window and door trim
4) install chimney and wood-burning stove
5) build counters, install sink and gas stove
6) finish screen porch
7) finish back porch
8) build master suite and bathroom
9) retire
10) everything else.

Monday, June 14, 2010

Roof and Rails

This weekend, we got the metal on the porch roof. The job would be finished if the supplier had not given us ridge cap instead of rake angle.



Also some hand rail and a kitchen sink drain were installed. The hand rail was the last bit of the salvaged deck that Carolyn and I brought up a couple of years ago. Another successful use of "found materials".





As soon as the gas line is installed for the stove, we can finish the sheetrock.