Fun's over! Back to work, June and July
Jun 28-29
Rented the trencher and jack hammer again and dug the trench for the well line. Hit a big patch of unbreakable rock 15 feet from the well head so there is a 3 foot stretch is only about 12" below the surface. The good thing is that this line will be drained most of the time.
Jul 12-13
Finished gluing together lengths of 1" pipe and laid it all in the trench. Started covering some of the trench near the cabin. Carolyn began to prime windows for the shop.
Jul 26-27
Dug out the hole for the valve box. Laid the 2" supply and drain lines.
Aug 16-17
Carolyn primed more shop windows while I connected the 2" line to the tank.
Aug 23-24
Made up all the connections in the valve box. Ran the well line up to the tank. It does not connect to the tank because the water requires treatment before going into the tank (see the discussion under
Hot Showers On-Demand).
Also, I installed a yard hydrant on the well line equidistant between the cabin and the shop to provide for:
Diverting well flush water to the garden
High-pressure fire hose
Draining the line