The plan is simple...doubled 2x10s sandwiching the sets of posts fastened with 5/16 lag screws. Bridging blocks are nailed between these on 16" centers. To each 2x10 is nailed a 2x4 ledger strip on which the 2x6 joists will rest. Blocks of 2x2 are nailed to each side of each end of each joist to prevent rolling. Here is the basic structure...
Four bays of 19 joists each plus a closing band at each end to accommodate walls between the posts (I still have to add extra joists and blocks down the sides for the same purpose). Sometimes the wood is a little crooked and you have to use gentle force to get it straight.
Next trip, I plan to lay down the subfloor. I haven't decided yet on the material - planks, plywood, or OSB. What do you think?
Now let me share a couple of critters with you that I encountered while on this job...